ABADAN

of the Abadan Refinery’s power grid, uninterrupted production of petroleum products, and providing emergency power to Phase 2 of the refinery, which will enable power exchange with the national power grid. This substation is also the first GIS 132 kV substation between the Abadan Refinery and the Khuzestan Regional Electricity

Employer

Abadan Oil Refining Company

Consultant

Qods Niroo

Contractor

Moham Sharq Holding

Special conditions and objectives

This project will be constructed to increase the capacity of the Kefisheh substation from 57 megavolt-amperes to 100 megavolt-amperes, as well as to reduce planned outages and develop power supply infrastructure for the industrial, commercial and residential sectors.

As part of this project, two 132.33 kV GIS substations will be constructed in two separate areas inside the refinery, with about 5 kilometers of trench between the two substations, indicating the large amount of employment it will create and will play a key role in the development of the country's infrastructure.

Project Gallery

With synergy among Maham Shargh Holding's subsidiaries and relying on the organizational belief "We can", Metanco is not only an implementer, but also a reliable partner for the sustainable and smart development of Iran's industrial infrastructure.
×